PW-SEV/BRG 500kV transmission project

The Arizona Corporation Commission (ACC) voted unanimously (5-0) to approve a Certificate of Environmental Compatibility (CEC) for the Pinal West to Southeast Valley/Browning (PW-SEV/BRG) project. The ACC reached its decision on Aug. 16, 2005 after completing the decision process. The Commissioners approved a route that slightly differs from the route recommended by the Line Siting Committee, specifically in the Coolidge area.

Request to expand 500kV power line corridor in Pinal Co.

On April 4, 2008, SRP filed a motion to amend the decision of the ACC (2.1MB PDF) regarding the CEC that calls for expanding the permitted corridor width west of the Pinal South substation and requests expedited consideration.

ACC hearings
On April 24, 2008 at an ACC open meeting, the Commissioners voted to consider SRP's request to expand the permitted corridor width west of the Pinal South substation and referred the matter to the Hearing Division for all future proceedings. On May 9 the Hearing Division issued a procedural order (735K PDF) that schedules a public comment meeting and evidentiary hearing.

ACC public comment meeting
The ACC will hold a public comment meeting on May 20, 2008 beginning at 7:00 p.m. at the Pinal County Fairgrounds, located at 512 South Eleven Mile Corner Road in Casa Grande. The public is invited to attend and provide input on SRP's request. SRP and the County will be in attendance at the meeting to answer any questions from the public.

ACC formal hearing

The ACC will also hold a formal hearing on SRP's request on May 30, 2008 beginning at 10 a.m. at the ACC offices located at 1200 West Washington Street, in downtown Phoenix. The public is also invited to attend this hearing. The Commissioners may vote on the matter at the conclusion of the formal hearing or may schedule a meeting for a later date to vote on SRP's request.

Landowners/homeowners located near the affected area should receive two mailings providing details on the public comment meeting and the formal hearing:

Approved route map
The ACC approved a modified route. View a map of the ACC's approved route (3.6MB PDF).

Approved CEC
Review the ACC's August 2005 CEC decision (2.4MB PDF) and the amendment to such that widens the corridor width for certain portions of the project in the Florence area.

Maps of ACC approved corridor width for design

Project fact sheet
View the project fact sheet. (256K PDF)

Construction updates

In accordance with the 500kV CEC condition #25, packets depicting the line route, depicting the poles and announcing the June energization of the Browning to Dinosaur segment were mailed to the developers and homebuilders within one mile of this portion of the line route the week of April 23, 2007.  Additional information will be mailed as future line segments near completion.

Copies of the materials mailed are available in PDF format below:

Construction schedule

Portion of Transmission Line Completion Date
Browning to Dinosaur energized by summer 2007
Palo Verde to Pinal West energized by summer 2008
Pinal West to Dinosaur energized by summer 2011

Back to top of page

Requests for reconsideration

Since the CEC was approved by the ACC, four requests for reconsideration were submitted.

On Sept. 28, 2005 the ACC held a special open meeting for the purpose of considering the four Applications for Rehearing of Decision No. 68093. The Pulte Homes' Application for Rehearing/Reconsideration was the only application discussed at the meeting. The other applications were deemed denied due to lapse of time.

View the requests:

Following discussion of the Pulte Application for Rehearing/Reconsideration, the Commissioners voted unanimously to grant the Pulte application and to consider the request for an expanded corridor width for the area from Node 81 south to the northern bank of the Gila River at a future ACC meeting to be determined. The Commissioners requested that Pulte and interested parties file a brief with the ACC clarifying their position on the Pulte request within 10 days.

View the briefs filed in the Pulte request for reconsideration:

The ACC held a special open meeting Nov. 9, 2005 at which the Commission voted unanimously on the Pulte request for reconsideration of the CEC decision. The amended decision extends the 500kV transmission line corridor width to a half mile on the east side of the centerline of the Valley Farms/Cooper Road section line, but for only the area that is north of the state land to the Union Pacific Railroad. Pulte's original request was to expand the corridor width to include the state land as well as the land located south of the state land to the north side of the Gila River.

Back to top of page

Project news

View the latest news about the project.

Hearings conducted

Line Siting Committee hearings 2004-05
The public was invited to participate in public hearings before the Arizona Power Plant and Transmission Line Siting Committee on the following dates:

  • Nov. 29-30, 2004 (overview)
  • Dec. 16-17, 2004 (Area A)
  • Jan. 7, 2005 (Area A)
  • Jan. 10-11, 2005 (Area B)
  • Feb. 14-15, 2005 (Area C)
  • March 9-10, 2005 (Area C)
  • March 22-23, 2005 (Area C)
  • April 8, 2005 (Area C)
  • April 14-15, 2005 (Area C)
  • May 10, 2005 (final)
  • June 7, 2005 (hearing reopened) - View details in the project timeline

On May 10, 2005, the siting committee recommended a CEC for the project.

Arizona Corporation Committee hearings
The public was invited to participate in public hearings before the ACC on the following dates:

  • July 13, 2005
  • July 20, 2005 (special public comment session held in Casa Grande)
  • Aug. 15-16, 2005

The ACC voted unanimously to confirm a CEC for the project on Aug. 16, 2005.

Back to top of page

Route tours completed

A tour of the Area A route was conducted on Jan. 20 (view a tour map - 211K PDF*). A tour of Area B was conducted March 2 (view a tour map - 1MB PDF*). A tour of Area C, Option 1 was conducted March 29 (view a tour map - 8.7 MB PDF*)

Hearing transcripts

Copies of transcripts from the following CEC hearings can be viewed at the Casa Grande Public Library:

  • Nov. 29-30, 2004
  • Dec. 16-17, 2004
  • Jan. 7, 10-11, 2005
  • Feb. 14-15, 2005
  • March 9-10, 2005
  • March 22-23, 2005
  • April 8, 2005
  • April 14-15, 2005
  • May 10, 2005
  • June 7, 2005

The library is located at 449 N. Dry Lake in Casa Grande.

Back to top of page

CEC application

On Oct. 7, 2004, SRP submitted an application for a Certificate of Environmental Compatibility (CEC) with the Arizona Corporation Commission (ACC) for the Pinal West to Southeast Valley/Browning (PW-SEV/BRG) project.

You can view selected parts of the application online:

A complete copy of the application, including detailed maps of the proposed project, is on file with Docket Control Center of the Arizona Corporation Commission at:

Arizona Corporation Commission
1200 West Washington, Suite 108
Phoenix, AZ 85007

Copies of the application are also available for inspection at the following locations:

  • City of Casa Grande Public Library - 449 N. Dry Lake, Casa Grande

  • City of Coolidge Public Library - 160 W. Central Avenue, Coolidge
  • City of Maricopa Public Library - 44240 W. Maricopa, Maricopa
  • City of Eloy Public Library - 100 East Seventh Street, Eloy
  • City of Queen Creek Public Library - 22407 S. Ellsworth Road, Queen Creek
  • City of Apache Junction Public Library - 1177 North Idaho Road, Apache Junction
  • City of Mesa Public Library - 64 East First Street, Mesa
  • City of Florence Public Library - 1000 South Willow Street, Florence

Back to top of page

Detailed project maps

View the most recent maps of the PW-SEV/BRG project below in PDF* format. For closer detail, please use the magnifying glass icon centered at top of the map to zoom in.

Approved route map - Modified route approved by ACC on Aug. 16, 2005 (1.6MB PDF*)

Recommended route map - Route recommended by siting committee on May 10, 2005 (969K PDF*)

Preferred alignments and alternatives - submitted with the CEC application Oct. 7, 2004 (492K PDF*)

Study area:

The maps below show maps of the larger study area including both the PV-PW and PW-SEV/BRG projects.

PV-SEV/BRG (formerly PW-SEV/BOB) project study area
Web version   PDF version* (534K)

CATS/PV-SEV map (672K PDF*)

Back to top of page

Project background

Find out more about what the project entails, its origin and the public process, and information about electromagnetic fields (EMF).

Contact us

If you have questions or comments about the project, please contact us.Comuníquese con nosotros

E-mail: Send questions to webmaster@azpower.org.

Telephone: Call SRP Public Involvement at (602) 236-2872 or (800) 380-6123.

Information request form: For questions about the project, complete our online request for information form.