PW-SEV/BRG 500kV transmission project

The Arizona Corporation Commission (ACC) voted unanimously (5-0) to approve a Certificate of Environmental Compatibility (CEC) for the Pinal West to Southeast Valley/Browning (PW-SEV/BRG) project. The ACC reached its decision on Aug. 16, 2005 after completing the decision process. The Commissioners approved a route that slightly differs from the route recommended by the Line Siting Committee, specifically in the Coolidge area.

Approved CEC

Approved route map
The ACC approved a modified route. View a map of the ACC's approved route (3.6MB PDF).

View the CEC decision
Review the ACC's August 2005 CEC decision (2.4MB PDF) and the amendment to such that widens the corridor width for certain portions of the project in the Florence area.

Maps of ACC approved corridor width for design

Project fact sheet
View the project fact sheet. (256K PDF)

Back to top of page

Construction schedule

Portion of Transmission Line Completion Date
Randolph to Dinosaur/Browning (230kV) energized by Sept. 1, 2010
Pinal West to Santa Rosa energized by April 2014
Santa Rosa to Pinal Central energized by April 2014
Pinal Central to Abel to Dinosaur to Browning (500/230kV) energized by April 2014

Back to top of page

Project background

Find out more about what the project entails, its origin and the public process, and information about electromagnetic fields (EMF).

Back to top of page

ACC approves request to add 230kV double circuit

On Nov. 19, 2008, the ACC issued Decision No. 70610 approving SRP's request to include a 230kV circuit on the 500kV structures:

  • From the Santa Rosa/Test Track Substation to a point on Cornman Road, near the intersection with Thornton Road (segment identified in green on map); and


  • From the Pinal Central (formerly Pinal South) Substation to the Abel (formerly Southeast Valley) Substation (segment identified in blue on map).

SRP made the request in a June 30, 2008 compliance filing to the ACC (under Condition No. 23 of the CEC).

With the Commission's approval of these two segments of 230kV circuit, the transmission line for the certificated route from Santa Rosa to Abel will be 500/230kV double circuit. The Commission previously approved the 230kV segment from Thornton Road (on Cornman Road) to the Pinal Central Substation in December 2006 (Decision No. 69183) under a separate Condition No. 23 filing.

View the application filed with the ACC on June 30, 2008 below. For ease of use, the filing is separated into three parts:

Request to expand 500kV power line corridor in Pinal County

On June 4, 2008 the Commissioners voted to deny SRP's request to expand the corridor width west of the Pinal Central (formerly Pinal South) substation (near the Pinal County Fairgrounds). As a result, the original route approved in the August 2005 CEC decision remains in effect. That route will traverse along the south side of Laughlin Road alignment from Curry Road to Eleven Mile Corner Road, crossing through the Pinal County Fairgrounds just north of the oval track, and then into the Pinal Central (formerly Pinal South) Substation.

Construction of the line in this area is anticipated to begin in 2013 with an anticipated in-service date of 2014.

View a map of the certificated route

Background on motion to amend

On April 4, 2008, SRP filed a motion to amend the decision of the ACC (2.1MB PDF) regarding the CEC that called for expanding the permitted corridor width west of the Pinal Central (formerly Pinal South) substation and requested expedited consideration.

ACC hearings
On April 24, 2008 at an ACC open meeting, the Commissioners voted to consider SRP's request to expand the permitted corridor width west of the Pinal Central (formerly Pinal South) substation and referred the matter to the Hearing Division for all future proceedings. On May 9 the Hearing Division issued a procedural order (735K PDF) that scheduled a public comment meeting and evidentiary hearing.

ACC public comment meeting
The ACC held a public comment meeting on May 20, 2008 beginning at 7 p.m. at the Pinal County Fairgrounds, located at 512 South Eleven Mile Corner Road in Casa Grande. The public was invited to attend and provide input on SRP's request. SRP and the County were in attendance at the meeting to answer any questions from the public.

ACC formal hearing

The ACC also held a formal hearing on SRP's request on May 30, 2008 at 10 a.m. at the ACC offices located at 1200 West Washington Street, in downtown Phoenix. The public was also invited to attend this hearing. The Commissioners held a special open meeting on June 4, 2008 to vote on the matter (view the meeting notice).

Landowners/homeowners located near the affected area were sent two mailings providing details on the public comment meeting and the formal hearing:

Back to top of page

Contact us

If you have questions or comments about the project, please contact us.

E-mail: Send questions to webmaster@azpower.org.

Telephone: Call SRP Public Involvement at (602) 236-2872 or (800) 380-6123.

Information request form: For questions about the project, complete our online request for information form.


Back to top of page



*To view PDF files, you'll need Adobe Acrobat Reader if you don't have it. It is free and you will only need to download it once. Then, return to this page to view the report sections and maps.

SRP -- Delivering more than power